Below is the current status of construction projects still considered active in Stark County. The Public Information Office will continue to notify you of any changes in lane restrictions and/or closures as they occur. 

As in previous years, we will no longer issue the weekly construction traffic advisory during the winter months.  When the new construction season begins in spring 2019 we will again issue weekly advisories.



State Route 619 in the Village of Hartville & Lake Township 
(Friday, November 30 Monday, December 3)
King Church Ave. at SR 619 is closedthrough Monday evening, December 3, for roundabout construction. The detour is SR 619 to Market Ave. to Lake Center St.

 



State Route 619 in the Village of Hartville & Lake Township
(Friday, November 30 Monday, December 3)
The following traffic pattern is in place at SR 619 and Kaufman Rd. through Monday evening, December 3:

Motorists traveling SR 619 eastbound are NOT able to access Kaufman Rd. northboundSouthbound Kaufman Rd. can only access SR 619 westbound. 
This work is part of a $10 million project to widen SR 619 between Kaufman Ave. and Milan Ave. The project also includes the placement of roundabouts at the SR 619 and Kaufman Ave. and SR 619 and Kings Church Ave. intersections. The entire project is scheduled to be completed by late June 2020.



Interstate 77 in the City of Canton & Plain Township
(until further notice)
The ramp from I-77 northbound to SR 687/Fulton Rd. is reduced to one lane for ramp widening through late December.
(until further notice)
SR 687/Fulton Rd. between Broad Ave and Park Dr. NW has various daily lane restrictions though late December for resurfacing and traffic signal upgrades. This work is part of a $3.7 million project to widen and resurface the northbound and southbound ramps at the I-77 and SR 687/Fulton Rd. interchange. The entire project is scheduled to be complete by late May 2019.